MARKETING  INFRASTRUCTURE  &  AGRICULTURAL 
 MARKETING  REFORMS

                                                                                            
 
                       
                                                                                           
      

Annexure-III
PROJECT OUTLAY FOR RYTHU BAZAR
AMOUNT (Rs. Lakh)
Sl. No. Particulars Quantity   Rate   AMOUNT (Rs. Lakh) Remarks
1 Land 2 acres LS 15.43 Cost of land restricted to 20% of the total project cost as per the Operational Guidelines of the CISS for Market Yards
2 Land leveling and development   LS 2.00  
           
3 Civil Construction *        
(a) Compound wall 400 rmt 1500 Rs/rmt 6.00  
(b) Internal walkways and approach road 800 sq.m 300 Rs/sq.m 2.40  
(c) Parking space 3000 sq.m 10 Rs/sq.m 0.30  
(d) Stalls along compound walls 800 sq.m 1800 Rs/sq.m 14.40  
(e) Stalls along independent walls 365 sq.m 2500 Rs/sq.m 9.13  
(f) Office building 15 sq.m 4000 Rs/sq.m 0.60  
(g) Utility buildings like toilet space, drinkig water trough, guard room, etc. 100 sq.m 4000 Rs/sq.m 4.00  
(h) Supplementary civil cost for items like gate, grills, shutters etc.   LS 1.00  
           
4 Services such as internal/ external electrification, water supply and sanitary system etc.   LS 9.96 Assuming the same to be = 25% of civil construction cost, land levelling and land development charges
           
5 Computer, printer, fax, phone etc.   LS 2.00  
           
6 Weights and weighing scales (200 nos.)   LS 2.00  
           
7 Preliminary and pre-operative expenses   LS 5.00  
           
8 Contingencies @ 5 % for the items 2,3,4,5 and 6   2.94  
           
9 Total Project cost     77.15  
           
10 Margin Money contribution .@25% of Total project cost   19.29  
           
11 Eligible subsidy @25% of the Total project cost   19.29 No upper ceiling on the quantum of subsidy to state govt. agencies.
           
12 Bank loan without subsidy adjustment @75% of Total project cost   57.86  
13 Bank loan with subsidy adjustment @50% of Total project cost   38.58