REVISED OPERATIONAL GUIDELINES GRAMIN BHANDARAN YOJANA

(Effective from 26.06.2008)

 

 

 

 

 

1.                  BACKGROUND

 

It is well known that the small farmers do not have the economic strength to retain the produce with them till the market prices are favourable.  There has been a felt need in the country to provide the farming community with facilities for scientific storage so that wastage and produce deterioration are avoided and also to enable it to meet its credit requirement without being compelled to sell the produce at a time when the prices are low.  A network of rural godowns will enable small farmers to enhance their holding capacity in order to sell their produce at remunerative prices and avoid distress sales.  Accordingly, Grameen Bhandaran Yojana, a Capital Investment Subsidy Scheme for Construction / Renovation of Rural Godowns was introduced in 2001-2002 and extended upto 31.03.2007. The Scheme has now been approved for implementation during the years 2007–12, with modifications in its operational guidelines for new projects to be sanctioned after 26 /06 /2008. Accordingly, revised operational guidelines of the scheme are applicable for new projects sanctioned on or after 26 /06 /2008 to 31.03.2012.

 

 

2.         OBJECTIVES

 

The main objectives of the scheme include creation of scientific storage capacity with allied facilities in rural areas to meet the requirements of farmers for storing farm produce, processed farm produce  and agricultural inputs; promotion of grading, standardization and quality control of agricultural produce to improve their marketability; prevention of distress sale immediately after harvest by providing the facility of pledge financing and marketing credit;  strengthen agricultural marketing infrastructure in the country by paving the way for the introduction of a national system of warehouse receipts in respect of agricultural commodities stored in such godowns and to reverse the declining trend of investment in agriculture sector by encouraging private and cooperative sectors to invest in the creation of storage infrastructure in the country. 

 

3.         SALIENT FEATURES

 

Eligible Organizations

 

i)          The project for construction of rural godowns can be taken up by individuals, farmers, Group of farmers/growers, Partnership/ Proprietary firms, Non-Government Organizations (NGO’s), Self Help Groups (SHGs), Companies, Corporations, Co-operatives, Local Bodies other than Municipal Corporations, Federations, Agricultural Produce Marketing Committees, Marketing Boards and Agro Processing Corporations in the entire            country. Assistance for renovation of rural godowns will, however, be restricted to godowns constructed by cooperatives only.

 

Location

 

ii)         Under the scheme, the entrepreneur will be free to construct godown at any place, as per his/her commercial judgment except for  the restriction that it would be outside the limits of Municipal   Corporation area.  Rural godowns constructed in the Food Parks    promoted by the Ministry of Food Processing Industries shall also be eligible under the scheme for assistance.

 

Size

 

iii)         Capacity of a godown shall be decided by an entrepreneur.  However, subsidy under the scheme shall be restricted to a minimum capacity of 100 tonnes and maximum capacity of 10,000 tonnes.  No maximum ceiling on subsidy in the case of projects of rural godowns of Cooperatives assisted by NCDC.

 

iv)        Rural godowns of smaller size upto 50 tonnes capacity will also be eligible for subsidy under the scheme as a special case based on viability analysis depending on the topography/special requirement of the State/Region.  In hilly areas*, rural godowns of smaller size upto 25 tonnes capacity will also be eligible for subsidy.  For this,  NABARD will issue appropriate guidelines.

 

*where the project site is located at a height of more than 1000 meters above mean sea level.

 

Conditions for Scientific Storage

 

v)     Godowns built under the scheme shall be structurally sound on account of engineering considerations and functionally suitable to store the agricultural produce. The general conditions for scientific construction will be as follows:

 

       a)       The construction of godown shall be as per Central Public  Works Department/State Public Works Department   specifications or any other standard    
       specifications laid down in this behalf.   The godown shall be properly     ventilated, shall have well fitted doors, windows and ventilators and shall be   

                waterproof (control of moisture from floor, walls and roof etc.)

 

       b)    The godown structure shall have protection from rodents.

 

       c)    The godown shall have protection from birds (windows / ventilators with jali).

       d)    The openings of godown such as doors, windows etc. shall    be     designed in such a manner that the godown can be  sealed for effective fumigation etc.

 

        e)   The godown complex shall have an easy approach road, pucca internal roads, proper drainage, arrangements for effective control against fire and theft and
     also have arrangements for easy loading and unloading of stocks.

 

vi)        The entrepreneur may obtain a license to operate the godown, if so required by the concerned State Government, under the State Warehousing Act or any other relevant laws.  All Rural Godowns to be constructed under the Scheme in future, should be confirming to the technical specifications relating to the implementation of the Negotiable Warehouse Receipt System (NWRS). The rural godowns of 1000 tones capacity and more shall be considered as eligible for assistance under the Scheme, only on giving an undertaking alongwith the application that they would be implementing the Negotiable Warehouse Receipt System. DMI in consultation with the Department of Food and Public Distribution and NABARD shall modify godown specifications to meet the requirements of implementation of Negotiable Warehouse Receipt System and NABARD shall ensure that these specifications are in-built in the eligibility criteria for giving subsidy to the rural godowns of any size under the Scheme.

 

Credit Linked Assistance

 

 

vii)                 Subsidy  under  the  scheme  is  linked  to  institutional  credit  and  will be   available to only such projects as are financed by Commercial Banks, Regional Rural Banks, State Cooperative Banks (SCBs),  State Co-operative Agricultural and Rural Development Bank (SCARDBs), Agricultural Development Finance Companies  (ADFCs), North Eastern Development   Finance Corporation(NEDFI), Urban Cooperative Banks etc. Loan to the entrepreneurs from banks for the  construction of godowns would carry an adequate long-term repayment period.

 

viii)       Assistance under the scheme shall be available on capital cost of construction of godown including the cost of allied facilities like boundary wall, internal road, platform, internal drainage system, weighing, grading, packaging, quality certification, warehousing  facilities which are functionally required to operate the godown.

 

Pledge Loan Facility

 

ix)   The farmers keeping their produce in the godowns shall be eligible to avail pledge loan on hypothecation of their produce. The terms and conditions governing pledge loans viz. margin, rate of interest, period of pledge, amount etc. will be as per the guidelines issued by RBI/NABARD and as per normal banking practices followed by the financial institutions.

 

 

Training

 

x)       A general awareness programme on the scheme for the farmers and a training programme for the entrepreneurs for construction, maintenance and operation of rural godowns will be organized by the National Institute for Agricultural Marketing, Jaipur (NIAM) and other National/State level Institutions.

 

 

Implementation Period

 

xi)        Implementation of the scheme shall be continued beyond 31.03.2007 upto 31.03.2012.

 

xii)       The modified scheme will be applicable to all new projects for construction / renovation of rural godowns in respect of which loans are sanctioned on or after
26/06/2008  upto 31/3/2012.

 

Nodal Agency

 

xiii)        The scheme shall be implemented by the Directorate of Marketing and Inspection (DMI), an Attached Office of Department of Agriculture & Cooperation.  A list of Regional/ Sub Offices of DMI is enclosed at Annexure-VI.

 

Target

 

xiv)       Under the Modified Scheme, creation of new 85 lakh tonnes and renovation of 5 lakh tonnes of  rural storage capacity is targeted.(Total 90 Lakh M.T.)

 

xv)       The sanction of projects in a State would be restricted to a maximum of 18  lakh tonnes (20% of the total capacity of 90 lakh tonnes envisaged during the XI Plan), but in specific circumstances the unused quota of a State can be diverted to another State by a conscious decision taken by a Committee to be constituted in the Ministry of Agriculture for this purpose.     

 

xvi)      5 lakh tonnes  would be reserved for  small  farmers  and  5 lakh tonnes for cooperatives during the XI Plan but a conscious decision for diverting this
            reserved quota to other categories can be taken by the Committee to be constituted in the Ministry as stated above

 

Insurance

 

xvii)      It will be the responsibility of the owner of the godown to have the insurance for the godown.

 

Subsidy

 

xviii)     Rate of subsidy shall be:-

 

(a)     33.33% of the capital cost of the project in case of projects located in North – Eastern States,  hilly areas and those belonging to Women Farmers/ their self help groups / co-operatives and SC/ST entrepreneurs & their self-help groups/ Co-operatives subject to a maximum ceiling on subsidy of Rs.62.50 lakhNo maximum ceiling on subsidy in the case of cooperatives assisted by NCDC;

 

(b)        25% of the capital cost of the project      to all categories of farmers (Other than Women Farmers), agriculture graduates, cooperatives and State/ Central Warehousing Corporations subject to a maximum ceiling on subsidy of Rs. 46.87 lakhNo maximum ceiling on subsidy in the case of cooperatives assisted by NCDC;

 

(c)        15% of the capital cost of the project to all other categories of individuals, companies & corporations etc., subject to a maximum ceiling on subsidy of

Rs. 28.12 lakh; and

 

d)         25% of the capital cost of the project for renovation of godowns of cooperatives with assistance from NCDC.

 

xix)       Capital  cost  of  the  project  for  the purpose of subsidy  under the scheme shall be calculated as follows:

 

a)         For godowns up to 1000 tonnes capacity – Project cost as appraised by financing Bank or actual cost or Rs 2500/- per tonne of storage capacity,
            whichever is lower;

 

b)         For godowns exceeding 1000 tonnes capacity – Project cost as appraised by Bank or actual cost or Rs 1875/- per tonne of storage capacity, whichever is
            lower.  However, for godowns exceeding 10,000 tonnes capacity, the subsidy would be restricted to that admissible for capacity of 10,000 tonnes only, subject 
            to the relaxations made under para 3 (xviii) above for projects of the cooperatives
;

 

c)         For renovation of godowns by cooperatives with assistance from NCDC - project cost as appraised by Bank / NCDC or actual cost or Rs.625/- per
            tonne of storage capacity, whichever is lower.

 

xx)        No beneficiary shall draw subsidy for the godown project or any of its component  from more than one source.

 

xxi)       The capacity of godown shall be calculated @ 0.4 M.T. per cu. mtr.

 

Release of Subsidy

 

xxii)            Subsidy for the projects under the scheme shall be released through NABARD for projects financed by Commercial, Cooperative and Regional Rural Banks,
            ADFCs, SCBs, SCARDBs, NEDFI and scheduled PUCBs and other institutions eligible for refinance from NABARD and through NCDC for projects
            financed by NCDC or by Cooperative Banks in accordance with its eligibility guidelines.

 

 

Adjustment of subsidy in Borrower's Account

 

xxiii) The subsidy released to the bank / NCDC for an individual project will be   kept in a separate borrower-wise account. The adjustment of subsidy will be back ended. Accordingly, the full project cost including the subsidy amount, but excluding the margin money contribution from the beneficiary, would be disbursed as loan by the banks. The repayment schedule will be drawn on the loan amount in such a way that the total subsidy amount is adjusted after full bank loan component net of subsidy with interest is liquidated but not before 5 years from the date of disbursement of first instalment of loan.

 

No interest chargeable on subsidy portion

 

xxiv) The subsidy admissible to the promoter under the scheme will be kept in the Subsidy Reserve Fund Account (Borrower-wise) in the books of the financing banks. No interest would be charged on this by the Bank.  In view of this, for purposes of charging interest on the loan component, the subsidy amount should be excluded.  The balance lying to the credit of the subsidy reserve fund account will not form part of demand and time liabilities for the purpose of  SLR/CRR.

 

4.       INSTITUTIONAL LENDING

 

A.      Eligible Financing Institutions

 

          The eligible financing institutions under the scheme are:-

 

i)        Commercial Banks, Regional Rural Banks (RRBs), State Cooperative Banks (SCBs), State Co-operative Agricultural and Rural Development Banks (SCARDBs), Agricultural Development Finance Companies (ADFCs), Scheduled Urban Coop. Banks, North Eastern Development Finance Corporation (NEDFI), and such other institutions eligible for refinance by NABARD. 

 

ii)       NCDC and Cooperative Banks recognized by NCDC in accordance with its eligibility guidelines.

 

B.      Term  Loan

 

i)  Minimum 50% of the project cost (46.67% in case of NE States, hilly areas, Women Farmers/ their self help groups / co-operatives and SC/ST entrepreneurs & their self-help groups/ Co-operatives ) is to be raised as term loan from the financing banks. As the subsidy is back-ended, eligible amount of subsidy would be initially allowed as term loan to the beneficiary. The repayment schedule will be drawn on the total loan amount (including subsidy).  The subsidy amount will be adjusted after liquidation of bank loan (net of subsidy) but not before 5 years from the date of disbursement of first instalment of term loan. 

 

ii)       Depending upon the cash flow, the term loan would carry an adequate long term repayment period, not less than 5 years including a grace period of one year.

 

iii)      Rate of interest to borrowers on term loan shall be as per RBI guidelines.  Interest will be chargeable from the date of the first disbursement of loan.

 

iv)      The   financial   institution   may   also provide working capital separately for undertaking business by entrepreneurs.

 

v)       NCDC may follow its own norms for period of term loan, its  repayment, moratorium, interest rate etc.

  

5.         PATTERN OF ASSISTANCE

 

 i)         FOR PROJECTS FOR WHICH SUBSIDY ROUTED THROUGH NABARD

 

          Pattern of funding

 

 

Projects located in States/ areas other than NE States/ hilly areas, and projects not belonging to women farmers/ SC/ ST entrepreneurs & their self-help groups/ cooperatives                          

 

Projects located in NE States/ hilly areas**/ & projects belonging to Women Farmers***/ SC/ST entrepreneurs & their self help groups/ Co-operatives****

Source of finance           

Farmers@, Agriculture Graduates, Cooperatives and State / Central Warehousing Corporations.         

Individuals, Companies and

Corporations etc.

 

Owner's minimum contribution*    

25%

25%

 

20%

Subsidy from the Govt.         

       

25%

15%

 

33.33%

Term loan from  eligible  Financing institutions (Minimum)

50%

50%

46.67%

 

          @      Farmer is a person whose main source of income is from Agriculture.

 

*        Cost of land not exceeding 10% of the project cost can form part of the owner's contribution.

**       Where the project site is located at a height of more than 1000 meters above mean sea level.

***     In case of partnership/ co-ownership, the ownership of women partners/ members shall be to the extent of 50% or more in the project to consider an application under the category of women farmer.

        ****  SC/ST Cooperative to be certified by the concerned officer of the State Government.

 

          Mode of release

 

a) Advance subsidy:   50% of the subsidy amount will be released to NABARD by Deptt of Agriculture and Cooperation in advance. Accordingly NABARD would release subsidy to participating banks in advance for keeping the same in the Subsidy Reserve Fund Account of the concerned borrower.  This amount of 50% advance subsidy would be released by NABARD to the participating banks on submission of a project profile-cum-claim form (Annexure-I).

 

b) Final subsidy :  The remaining 50% of the subsidy amount would be disbursed to the participating bank(s) by NABARD after conduct of an inspection by a Joint Inspection Committee comprising of officers from NABARD, participating bank and Directorate of Marketing & Inspection (DMI) in the concerned State.

 

         ii)       FOR PROJECTS FOR WHICH SUBSIDY ROUTED THROUGH   NCDC

 

          Pattern of funding

 

For Cooperatives located in the States/ areas other than NE States/ hilly areas, and projects not belonging to women farmers/ SC/ ST entrepreneurs & their self-help groups/ cooperatives                          

 

From NCDC to State Govt. society

Term loan  -   65%

Subsidy     -    25%

From State Govt. to society

 

Term loan          -        50%

Share Capital     -       15%

Subsidy              -       25%

Society share     -       10%

 

 

For Cooperatives located in NE States/ hilly areas/ & projects belonging to Women Farmers/ SC/ST entrepreneurs & their self-help groups/ Co-operatives

From NCDC to State Govt. society

Term loan  -   56.67%

Subsidy    -  33.33%

From State Govt. to society

 

Term loan          -       50.00%

Share Capital     -       06.67%

Subsidy              -       33.33%

Society share    -        10.00%

 

          Through Cooperative Banks / directly to Cooperative Societies

 

S.No.

Source of Finance

Cooperatives located in the States/ areas other than NE States/ Hilly areas and cooperatives not belonging to women farmers/ SCs/ STs/ their self-help groups

Cooperatives located in NE States/ Hilly areas* and for Women Farmers/ their self help groups / co-operatives and SC/ST entrepreneurs & their Co-operatives   

i)       

Promoter's contribution

(Minimum)**

            

25%

20%

 

       ii)    

Subsidy from the Govt

25%

 

33.33%

      iii)

Term loan (Minimum)

                  

50%

46.67%

                                                                                                                                                 

*        Where the project site is located at a height of more than 1000 meters above mean sea level .

**      Cost of land not exceeding 10% of the project cost can form part of the owner's contribution.

 

          Mode of release

 

a)  50% of subsidy amount shall be released on approval and acquisition of land and balance 50% of subsidy amount shall be provided after godown has reached
     roof level.

 

b)  100% of subsidy amount shall be released in case of renovation of godowns after work of repair and renovation is taken up.

 

         c)  The subsidy provided as interest free loan shall be adjusted only after construction of godown has been completed to the satisfaction of NCDC.

 

6.       PLEDGE LOAN

 

 The farmers keeping their produce in the godowns shall be eligible to avail on hypothecation of produce upto 75% of the value of produce pledged subject to a ceiling of Rs.5 lakh per borrower.  Such loan shall be for a period of upto 12 months. The rate of interest on such loans shall be as per RBI guidelines.  The banking institutions shall accept the godown receipts on its being duly endorsed and delivered to bank for pledge loan against hypothecation of produce as per RBI guidelines.  The pledge loan advance under Grameen Bhandaran Yojana will qualify under 'Direct Agriculture - priority sector lending'.

 

7.       TIME LIMIT FOR COMPLETION

 

          A time limit of 15 months is prescribed for completion of the project from the date of disbursal of first instalment of loan.   However, if reasons for delay are justified, a further grace period upto 6 months may be allowed by the participating bank. If the project is not completed within stipulated period, the benefit of subsidy shall not be available and advance subsidy has to be refunded forthwith

 

8.       REFINANCE ASSISTANCE FROM NABARD

 

For Construction of Rural Godowns

 

For construction of rural godowns, NABARD would provide refinance, if required by commercial bank / RRBs/ ADFCs / SCBs/ SCARDBs and such other eligible institutions @ 90% of the amount financed by them as term loan.  However, quantum of refinance is 95% in case of  SCARDBs in North Eastern Region. The quantum of refinance from NABARD could vary from time to time.  Rate of interest on refinance will be as decided by NABARD from time to time.  

 

For Pledge Loan

 

          For Pledge Loan, NABARD will also provide refinance to Cooperative Banks as per NABARD's norms which are as under:

 

i)          Facility of pledge finance is extended to all cultivators whether they be the borrowing members of PACS or not and the DCCBs are permitted to directly finance individual cultivators on the strength of the pledge;

 

ii)         Quantum of pledge loan will be upto 75% of value of actual produce pledged subject to a ceiling of Rs.5 lakh per borrower;

 

iii)         The period of pledge loan is upto 12 months;

 

iv)        Farmers are given freedom to take back their produce once the pledge loan is repaid; and

 

v)         Rate of interest on re-finance against pledge loan will be as  decided by  NABARD from time to time.

 

9.       PUBLICITY AND TRAINING

 

The general awareness programme on the scheme for the farmers and the training programme for the entrepreneur for construction, maintenance and operation of rural godown will be organised by the National Institute for Agriculture Marketing, Jaipur in collaboration with other institutions like BIRD, TOPIC  etc.

 

10.     OTHER CONDITIONS

 

i)        Rural godowns may be treated as infrastructure for financing.

 

          ii)       The participating banks / NCDC / NABARD, etc., will adhere to their own  norms for appraisal of projects.

 

          iii)      A signboard at the site "Assisted under Gramin Bhandaran Yojana of Ministry of Agriculture, Government of India" will be exhibited.

 

          iv)      Govt.’s interpretation of various terms will be final.

 

          v)    Besides Joint Inspection Committee (JIC) inspection, pre & post completion inspections of the project may be undertaken to verify physical, financial and operational progress, as and when required.

 

          vi)      Govt.  reserves  the  right  to  modify,  add  and  delete  any  term and  condition without assigning any reason.

 

11.     PROCEDURE TO BE FOLLOWED FOR SANCTIONING OF PROJECT AND RELEASE OF SUBSIDY

 

          Projects financed through  Banks

 

   

            i)    Promoter will submit the project proposal for term loan and subsidy to Bank on application form as prescribed by the concerned Bank along with project
report and other  documents for appraisal and sanction of loan. A copy of the proposal shall also be endorsed by the promoter to Sub Office/ Regional Office of DMI as per list at Annexure VI.

 

ii)   Bank after appraisal and sanctioning of project and disbursal of first instalment of loan will furnish a brief project profile-cum-claim form for advance subsidy in the prescribed form given at Annexure-I along with a copy of bank’s sanction letter to RO, NABARD with a copy to the Sub Office/ Regional Office of DMI as per list at Annexure VI.

 

iii)   NABARD on receipt of project profile-cum-claim form from the participating bank, will sanction and release 50% advance subsidy to the participating bank for keeping the same in the Subsidy Reserve Fund Account (Borrower-wise).  NABARD will forward a copy of claim form as indicated in Annexure I to the Head Office of DMI project-wise for replenishment or adjustment against advance subsidy provided by DMI to NABARD. The release of subsidy by NABARD will be subject to availability of funds from DMI.

 

 

iv)   When the project is complete, the promoter will inform the bank which will initiate action for an inspection by a Joint Inspection Committee consisting of officials from bank, NABARD and DMI to ensure that the rural godown conforms to approved technical & financial parameters However, for rural godowns of upto 1000 MTs capacity, the Ministry of Agriculture will consult NABARD and subject to their willingness, the present system of having three members Committee would be continued, otherwise the Joint Inspection Committee for Rural Godowns of upto 1000 MT capacity, will be downsized  to only two officials, one from the bank concerned and the other one from the DMI.

 

v)   The Joint Inspection Committee shall consult the Head of the Gram Panchayat / Member of concerned Local Body before making recommendations for release of final subsidy for each project.

 

            vi)  After inspection is conducted, the bank will submit the claim form for final subsidy in the prescribed format given at Annexure II to NABARD, in triplicate,
  with a copy to Regional Office/Sub-Office, DMI.  The inspection report of Joint Inspection Committee and completion certificate should  invariably be enclosed
  with claim form for final subsidy. NABARD shall release the final subsidy to banks which will be replenished by DMI or adjusted against the subsidy amount
  provided to NABARD in advance.

 

          Projects financed through NCDC

 

i)      NCDC shall provide assistance to the cooperatives for  construction/renovation of godowns.

 

ii)     The cooperative societies shall formulate proposals in the format prescribed by NCDC and shall submit to RCS/State   Govt. or directly to NCDC.

 

iii)    The RCS/State Govt. shall examine the proposal and shall recommend to NCDC for consideration.

 

         iv)    NCDC shall   communicate  its  sanction to the State  Govt. and a   counter sanction shall be issued by the State Govt. to  the societies.

 

v)   The pattern of funding,  interest   rates,  mode  of  release of    sanctioned  assistance  shall  be as per NCDC’s norms and  policies as circulated from time to time.

         

vi)  The State Govt. shall periodically furnish progress report to  the NCDC and NCDC shall furnish the same to DMI.

 

vii)  DMI shall release advance subsidy   for   parking   in NCDC’s   account. The project-wise subsidy shall be adjusted / replenished by DMI.

 

viii)         NCDC shall furnish utilisation certificate to  DMI.

 

ix)            NCDC and DMI may undertake inspection of godowns to verify the utilization on a random basis.

 

12.     MONITORING

 

          i)       The monitoring of each project shall be done by DMI through its Regional/ Sub-Offices (Annexure VI) and review will be done on monthly basis with NABARD/NCDC.         

         

          ii)      As mentioned in para 11(iv), a Joint Inspection Committee consisting of officials from NABARD, NCDC, participating bank(s), as the case may be, and DMI would inspect the project within the overall scope of the operational guidelines of the scheme and would submit its report in the format at Annexure-V which should be enclosed with Annexure II.  For this purpose, the promoters/participating banks/NABARD/DMI will initiate necessary action to get the inspection conducted on the project site by the  Joint Inspection Committee as soon as the project is completed, so as to avoid any delay in release / adjustment of subsidy.

         

          iii)      After crediting the final instalment of subsidy in the reserve fund of the borrower, a utilization certificate as per Annexure III is required to be submitted by the participating bank to NABARD/ NCDC as the case may be to the effect that  amount of subsidy received by them has been fully utilized/adjusted in the books of account under the sanctioned terms and conditions of the project, within the overall guidelines of the scheme.

         

          iv)      The progress report of the scheme as per format at    Annexure – IV  shall be sent by NABARD / NCDC directly to the Head Office of DMI on   
                    monthly  basis.

 

         

 

***

 


Annexure –I

 

 

FORMAT FOR PROJECT PROFILE -CUM -CLAIM FORM FOR CLAIMING 50% ADVANCE SUBSIDY/REFINANCE

 

(TO BE SUBMITTED BY BANK IN TRIPLICATE TO NABARD WITH A COPY TO  DMI)

 

To

          (1)     Regional Office, NABARD

(2)          Regional/ Sub-office,

          (nearest, as per addresses enclosed)

                   Directorate of Marketing & Inspection,

                 

          CAPITAL INVESTMENT SUBSIDY SCHEME FOR CONSTRUCTION/ RENOVATION OF RURAL GODOWN.

 

PART- I

(For use by Bank)

 

1.       i) Name & address of project including Tehsil/Taluka/District

          ii) Whether located in NE States/Hilly areas i.e., above 1000 MSL

 

2.       i)  Name and address of promoter.

          ii) whether belongs to SC/ST / their cooperative, if yes, specify :

          iii) whether farmer*/agriculture graduate/SWC/CWC/Cooperative

                a) If farmer, whether a small farmer**

          iv) whether individual/company/corporation/others

 

*    farmer is a person whose main source of income is from Agriculture.

** Small farmer is a person having less than 2.5  acres of irrigated land or 5 acres of dry land.

 

3.       Entitlement of subsidy (15%/25%/33.33%)

 

4.     Name & address of financing bank

 

5.       Date of receipt of proposal/application.

 

6.       a)       Amount of loan sanctioned

         b)       Date of sanction of loan

          c)       Date of disbursement of first instalment

 

7.     Itemwise financial projections

                                                                    As per project           As appraised

                                                                    report     (Rs)             by  bank (Rs.)

          i)  Land

          ii) Godown

          iii) Allied facilities

               a) Boundary wall

               b) Internal road

               c) Others (to be specified)

 

                           Total outlay :                                                                                                  

 

8.       Means of finance

 

                                                                                                                                                                                   As per project            As appraised

                                                                    report     (Rs)             by  bank (Rs.)

 

          •        Promoters contribution

          •        Bank loan

          •        Any other source

 

                                            Total:

 

9.     Capacity of godown:

 

                                                            No. of chambers       Size             Capacity

                                                                                              (cu.mtrs)     (in tones)

i)               New unit to be created

          ii)       Existing unit, if any

ii)              Renovation of

         Cooperative godowns

                  

10.     Rate of interest ( to be charged)                                       %

 

11.   Brief coverage on technical

          feasibility and financial viability.

         

12.     Other relevant information including as to whether the godown would be for self use/to be leased out to private or Govt. agencies/to store farmers produce on rent and commodity to be stored.

 

13.     The project has been appraised and found to be technically feasible and financially viable.  We intend/do not intend to avail of refinance from NABARD.  The refinance amount is Rs._____________(if to be availed).

 

14.     An amount of Rs._________(Rupees__________________________) being the 50% of the eligible amount of subsidy may please be released in respect of the project for crediting to the “Subsidy Reserve Fund Account – Borrower-wise”.

 

15.     We note that a time limit of 15 months is stipulated for completion of the project from the date of disbursal of first instalment of loan.  If reasons for delay in completion of the project are justified, a maximum grace period of up to 6 months may be allowed for completion of project.  We also note that the advance subsidy has to be refunded forthwith if the project is not completed within the above stipulated period and as per the broad parameters of the scheme.  It is further noted

 

 

          that in case of any delay in refund of subsidy, the participating bank/beneficiary will be liable for payment of penal interest.  It is also confirmed that the project does not fall within a Municipal Corporation area.

 

                                                                                           (___________________)

Place :                                                                                      Seal and signature of the

Date:                                                                                Authorised signatory of Bank

 

Enclosures –    1) Project report

                         2) Land documents

                         3) Loan sanction letter issued by competent authority

                         4) Brief coverage on technical feasibility & financial viability

                         5) Proof of category

6) Affidavit of the beneficiary that he has not availed/shall not avail

     subsidy for the project from any other source.

 

PART-II

(For use of RO, NABARD)

 

(A) For use by RO, NABARD

Advance subsidy

 

          The claim of advance subsidy of Rs.______________ is forwarded herewith for release of the same.

 

Date:                                                                                        (_______________)

                                                                                                            Authorized signatory,

  Regional Office, NABARD.

(B) For use by NABARD

 

Scheme Code

State Code

District Code

 

Project Code

Bank Code

 

          An amount of Rs.______________ is released as advance subsidy on ___________(name of the bank) vide subsidy disbursement advise no.________________(copy enclosed).  This amount may please be replenished/adjusted by DMI.

 

Date: 

                                                                                               (_______________)

                                                                                                            Authorized signatory,

                                                                                        Head Office, NABARD.

(C ) For use by HO, DMI

 

          An amount of Rs._________________as advance subsidy against above mentioned claim is hereby released/replenished to NABARD vide D.D No.__________________dated _______________________drawn on  ________________(Bank)

                           

Date: 

                                                                                               (_______________)

                                                                                                            Authorized signatory,

                                                                                                                      Head Office, DMI          
 

Annexure – II

 

FORMAT FOR CLAIMING FINAL INSTALMENT OF SUBSIDY

 

(To be submitted by Bank in triplicate to NABARD with a copy to DMI)

 

To

          (1)     The Regional Office, NABARD/

(2)       Regional/ Sub-office,

          (Nearest, as per addresses enclosed)

                   Directorate of Marketing & Inspection,

         

CAPITAL INVESTMENT SUBSIDY SCHEME FOR CONSTRUCTION / RENOVATION OF RURAL GODOWN.

 

(For use by Bank)

 

1.       i) Name & address of project including Tehsil/Taluka/District

          ii) Whether located in NE States/Hilly areas i.e. above 1000 MSL

 

2.       i)  Name and address of promoter.

          ii) whether belongs to SC/ST / their cooperative, if yes, specify :

          iii) whether farmer*/agriculture graduate/SWC/CWC/Cooperative

                a) If farmer, whether a small farmer**

          iv) whether individual/company/corporation/others

 

*    farmer is a person whose main source of income is from Agriculture.

** Small farmer is a  person having less than 2.5  acres of irrigated land or 5 acres of dry    land.

 

3.       Entitlement of subsidy (15%/25%/33.33%)

 

4.     Name & address of financing bank

 

5.       Date of receipt of proposal/application.

 

6.       a)       Amount of loan sanctioned

         b)       Date of sanction of loan

          c)       Date of disbursement of first instalment

          d)       Date of disbursement of last instalment

          e)       Total loan amount disbursed

 

7.     Itemwise cost of project

                                                       As per project   As appraised            Actual cost    

                                                        report              by Bank         

                                                                                                                                                  

                                       i)  Land

          ii) Godown

          iii) Allied facilities

               a) Boundary wall

               b) Internal road

               c) Others (to be specified )

                           Total  :                                                                                                          

 

8.       Source of finance

 

                                                                                                                                                                                  As per project            As approved            Actual

                                                                    report     (Rs)             by  bank (Rs.)         (Rs.)

 

          •        Promoters contribution

          •        Bank loan

          •        Any other source

                                            Total

 

9.     Capacity:

                                                            No. of chambers       Size            Capacity

                                                                                             ( cu.mtrs).    (in tones)

i)        New capacity created

          ii)       Existing unit, if any

i)               Renovation of

         Cooperative godowns

                  

10.     Total entitlement of  subsidy                                           Rs.                        

 

11.     Amount of advance subsidy released                                    Rs.                                         

12.    Balance subsidy to be released                                             Rs.

13.     Date of sanction of refinance by NABARD

14.     Date of amount of refinance released by NABARD

15.     Construction/renovation has been carried out as per technical parameters    envisaged          under the project.

16.     Since the project is complete as per terms and conditions stipulated under the scheme and final inspection of godown has been conducted, an amount of Rs.____________________(Rupees _______________________) being the final instalment of subsidy may please be released  for crediting to the “Subsidy Reserve Fund Account – Borrower-wise”.

 

17.     The following documents are enclosed :-

          a)       Copy of Joint Inspection Committee Report.

          b)       Compliance report from bank, if any

          c)       Completion certificate signed by promoter and verified by Joint Inspection Committee.

          d)       Proof of category

 

         

                                                                                           (___________________)

 

Place :                                                                                      Seal and signature of the

                                                                                    Branch Manager of Bank

Date


 

 

 

PART-II

 

(For use of RO, NABARD)

 

(A) For use by RO, NABARD

 

          An amount of Rs._________________ as final instalment of subsidy towards the above claim of __________________(name of the bank) in respect of ______________________________(name of the project) may be released.

 

Date: 

                                                         (_______________)

                                                                                                            Authorized signatory,

Regional Office, NABARD.

(B) For use by NABARD

 

Scheme Code

State Code

District Code

 

Project Code

Bank Code

 

          An amount of Rs.______________ is released as final subsidy on ___________(name of the bank) vide subsidy disbursement advise no.________________(copy enclosed).  This amount may please be released by DMI.

 

Date: 

                                                                                              (_______________)

                                                                                                            Authorized signatory,

                                                                                        Head Office, NABARD.

(C ) For use by HO, DMI

 

          An amount of Rs._________________as final subsidy against above mentioned claim is hereby replenished/adjusted  to NABARD vide D.D No.__________________            dated _______________________drawn on  ________________(Bank)

                           

Date: 

                                                                                                    (_______________)

                                                                                                            Authorized signatory,

                                                                                             Head Office, DMI           
 

 

Annexure III

 

      

FORMAT FOR UTILIZATION CERTIFICATE

 

(FOR THE USE OF FINANCING BANK TO BE SUBMITTED, IN TRIPLICATE, TO THE REGIONAL OFFICE OF NABARD)

 

CAPITAL INVESTMENT SUBSIDY SCHEME FOR CONSTRUCTION/ RENOVATION OF RURAL GODOWNS

 

 

1. Name, address/location of the                        

    project:

 

2. Name and address of the beneficiary :

 

3. Name and address of the financing bank :

 

4. Date of sanction of loan by bank :

 

5. Date of inspection by Joint Inspection Committee :

 

6. Date of completion of the project :                             

 

7. (i) Total financial outlay                                              - Rs.

 

    (ii) Margin money                                                      - Rs.

 

    (iii) Bank loan                                                            - Rs.

 

    (iv) Subsidy received Date of receipt           Amount       Date of credit to the

                                                from NABARD                    (Rs.)            Subsidy Reserve                                                                                                             Fund A/c of the                                                                                                             Borrower

 

(a) 50% Advance Subsidy

 

(b) Final installment of subsidy

                                                                                    ----------

       Total

                                                                                    ======

 

 

8. (i) Capacity created   

 

                                        Volume             Capacity       No. of Chambers

                                         (cubic mtrs.)  (In tonnes)

 (a) New Unit

                                                                                                              

 (b) Renovation

 

9. Rate of interest charged by financing bank      -           % p.a.

    a) In the case of CBs            -PLR    -                                   % P.A.

 

    b) In the case of others-

        PLR of Convener bank of SLBC

 

10. The bank has/has not availed of refinance from NABARD.

 

11. This is to certify that the full amount of subsidy received in respect of the above project has been fully utilized (by way of crediting to the “Subsidy Reserve Fund Account – Borrower-wise) and adjusted in the books of account under the sanctioned terms and conditions of the project and within the overall guidelines of the scheme.

 

 

 

 

Place

 

Date                                                                             Seal and Signature of the

                                                                      Branch Manager (Financing bank)


 

 

Annexure-IV

 

 

PROGRESS OF CAPITAL INVESTMENT SUBSIDY SCHEME FOR RURAL GODOWNS

 

SANCTIONED/PENDING SCHEME (ABSTRACT)*

 

 

STATUS AS ON _________

 

 

 

Sl.No.

State

Name of the project

Location

Capacity

(tonnes)

TFO

Sanct-ioned

Bank

loan

Promoter’s

Contributi-on

Total

eligible

subsidy

Subsidy released to financing banks

 

 

 

 

 

 

 

 

 

Adva-nce

Final

Total

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

* The above information break-up may be furnished for projects sanctioned to farmers/small farmers/SC/ST entrepreneurs and their cooperatives separately.

 

 

 

Annexure-V

 

 

 

PROFORMA FOR JOINT INSPECTION REPORT OF GODOWN CONSTRUCTED UNDER GRAMEEN BHANDARAN YOJANA

 

 

 

                                                                        Date of Inspection :

 

 

1.       Members of Joint Inspection Committee

 

          Organization                    Name               Designation                   Address

         

          i)   NABARD

          ii)  Financing bank 

          iii) DMI

 

2.       i) Name & address of project including Tehsil/Taluka/District

          ii) Whether located in NE States/Hilly areas i.e., above 1000 MSL

 

3.       i)  Name and address of promoter.

          ii) whether belongs to SC/ST / their cooperative, if yes, specify :

          iii) whether farmer*/agriculture graduate/SWC/CWC/Cooperative

                a) If farmer, whether a small farmer**

          iv) whether individual/company/corporation/others

 

*    farmer is a person whose main source of income is from Agriculture.

** Small farmer is a  person having less than 2.5  acres of irrigated land or 5 acres of dry    land.

 

4.       Rate of entitlement of subsidy i.e. 15% / 25% / 33.33%

 

5.       Use of godown 

 

          i)    Own use/to store farm produce on rental/to be

                leased out to private or Govt. agency

           ii)  Commodity(ies) to be stored

 

6.     Name & address of financing bank

 

7.     i) Date of sanction of loan

       ii) Amount of loan sanctioned

      iii) Date of disbursement of first instalment

       iv) Date of disbursement of last instalment

        v) Total loan amount disbursed

 

 8.    i)  Date of completion of the project            

        ii)  Date of intimation of completion to NABARD & DMI

 

 

9.     Item-wise cost of project

 

                                                    As per Project Report     As appraised                         Actual   

                                                                                          by Bank        

                         

                                           i)   Land

           ii) Godown

           iii) Allied facilities

            a) Boundary wall

             b) Internal road

             c) Others (to be specified )

                          

                   Total  :                                                                                                      

 

10.     Source of finance

 

                                                              As per project            As approved            Actual

                                                               report     (Rs)            by  bank (Rs.)         (Rs.)

 

          •        Promoters contribution

          •        Bank loan

          •        Any other source

 

                                            Total

 

11.    Capacity:

 

                                                            No. of chambers       Size             Capacity

                                                                                            (cu.mtrs.)    ( in tonnes)

i)        Capacity created

          ii)       Existing unit, if any

i)               Renovation of

         cooperative godowns

                  

12.     Total entitlement of subsidy                                     Rs.                        

 

13.     Amount of advance subsidy released                        Rs.                                         

 

14.     Balance subsidy to be released                                 Rs.

 

15.     a)  Whether project completed in time      

b) Whether construction/renovation has been carried out as per technical  parameters envisaged under the scheme,

          c)  If not, please specify the deviation(s).

          d)  Whether the godown has been insured

 

16.     Recommendations of the Joint Inspection Committee

 

 

(Signature and date)  

 

(i)   NABARD                                     

(ii)  Financing Bank                              

(iii)  DMI

 

 

 

Annexure VI

 

LIST OF REGIONAL / SUB-OFFICE OF DIRECTORATE OF MARKETING & INSPECTION WITH ADDRESSES

 

 

Andaman & Nicobar Island

 

Asstt.Agricultural Marketing Adviser,

Directorate of Marketing & Inspection,

General pool Offices Building,

4th Floor, A Wing, DF Block,

Sector-1,Salt Lake,

Kolkata-700064

Ph.033-23340845, 23347553

 

Andhra Pradesh

 

Asstt. Agricultural Marketing Adviser,

Directorate of Marketing & Inspection

Kendriya Sadan,  2nd  Floor

Sultan Bazar, Hyderabad-500095

Ph.040-24657446, 24731637

 

Arunachal Pradesh

 

Asstt. Agricultural Marketing Adviser,

Directorate of Marketing & Inspection

Regional Office, Rukminigaon,

Navaratna Path, House No. 09,

1st Floor, P.O. Khanapara

Guwahati-781 022 (Assam)

Ph.0361-2229272, 2229273

 

Assam

 

Asstt. Agricultural Marketing Adviser,

Directorate of Marketing & Inspection

Regional Office, Rukminigaon,

Navaratna Path, House No. 09,

1st Floor, P.O. Khanapara

Guwahati-781 022 (Assam)

Ph.0361-2229272, 2229273

 

Bihar

Asstt. Agricultural Marketing Adviser,

Directorate of Marketing & Inspection

Nagina Niketan OPP. A.N.College,

Boring Road Patna-800013

Ph. 0612-2266691

Chandigarh

 

Asstt. Agricultural Marketing Adviser

Directorate of Marketing & Inspection,

6th Floor, Kendriya Sadan,

Sector 9 ‘A’,

Chandigarh-160 047

Ph.0172 – 2743201

 

Chhatisgarh

 

Asstt. Agricultural Marketing Adviser

Directorate of Marketing & Inspection,

33, Anand Nagar,

RAIPUR, Chhatisgarh.

Ph. 0771-2446030

 

 

Dadra & Nagar Haveli

 

Asstt Agricultural Marketing Adviser,

Directorate of Marketing & Inspection

New CGO Building, 3rd Floor,

New Marine Lines,

Mumbai-400020

Ph.022-22036801,22032699

 

 

Daman & Diu

Asstt. Agricultural Marketing Adviser,

Directorate of Marketing & Inspection

New CGO Building, 3rd Floor,

New Marine Lines,

Mumbai-400020

Ph.022-22036801,22032699, 22037350

 

Delhi

 

Asstt. Agricultural Marketing Adviser,

Directorate of Marketing & Inspection

W-6, Okhla Industrial Area,

Phase-II, New Delhi-110020

Ph.011-26387284, 011-26387285 ,011-26387286

 

Gujarat

Senior Marketing Development Officer,

Directorate of Marketing & Inspection

1, Inderprastha Society

1st Floor, Near Gandhi Bridge

Shahpur, Ahmedabad-380004

Ph. 079-25660965

Goa

 

Senior Marketing Officer,

Directorate of Marketing & Inspection

APMC Complex, Arlem,

Raja Salcete, Margao

Goa-403720

Ph. 0832-2743589

 

Haryana

 

Asstt. Agricultural Marketing Adviser,

Directorate of Marketing & Inspection

W-6, Okhla Industrial Area,

Phase-II, New Delhi-110020

Ph.011-26387284, 011-26387285 ,011-26387286

 

Himachal Pradesh

 

Asstt. Agricultural Marketing Adviser,

Directorate of Marketing & Inspection

6th floor Kendriya Sadan,

Sector 9’A’ Chandigarh-160047

Ph.0172-2743201

 

Jammu & Kashmir

 

Senior Marketing Officer

61,A, II Extension, Gandhi Nagar,

Jammu Tawi-180004

Ph. 0191-2450478 (O)

 

Jharkhand

 

Senior  Marketing Officer,

Directorate of Marketing & Inspection,

Main Terminal Market Yard,

Pardra, RANCHI-4.

      Ph.: 0651- 2512597

 

Kerala

Senior Marketing Officer,

Directorate of Marketing & Inspection

T.C.No.25/1107 (6)

2nd Floor, Ramakrishna Building,

Near Manorama, Tampanoor

Thiruvanathapuram-695001

Ph. 0471-471134

 

 

 

Karnataka

Asstt. Agricultural Marketing Adviser,

Directorate of Marketing & Inspection

M.G.Complex APMC,

Yashwantpur,

Bangalore-560080

Ph. 080-23473004

 

Lakshadweep

 

Senior Marketing Officer,

Directorate of Marketing & Inspection

T.C.No.25/1107 (6)

2nd Floor, Ramakrishna Building,

Near Manorama, Tampanoor

Over Bridge Junction, East Thampanoor,

Thiruvanathapuram-695001

Ph. 0471-471134

 

Maharashtra

 

Asstt.Agricultural Marketing Adviser,

Directorate of Marketing & Inspection

New CGO Building, 3rd Floor,

New Marine Lines,

Mumbai-400020

Ph.022-22036801,22032699, 22037350

 

 

Madhya Pradesh

Asstt. Agricultural Marketing Adviser,

Directorate of Marketing & Inspection

Regional Office, 245, 2nd Floor,

MP Nagar, Zone-II,

Bhopal-462 011

Ph.0755-2551847

 

 

Manipur

Asstt. Agricultural Marketing Adviser,

Directorate of Marketing & Inspection

Regional Office, Rukminigaon,

Navaratna Path, House No. 09,

1st Floor, P.O. Khanapara

Guwahati-781 022 (Assam)

Ph.0361-2229272, 2229273

 

Meghalaya

Marketing Officer,

Directorate of Marketing & Inspection

Kher Malki Road, Dhankheri,

Shillong-793001

Ph: 0364-2503017

 

Mizoram

Asstt. Agricultural Marketing Adviser,

Directorate of Marketing & Inspection

Regional Office, Rukminigaon,

Navaratna Path, House No. 09,

1st Floor, P.O. Khanapara

Guwahati-781 022 (Assam)

Ph.0361-2229272, 2229273

 

Nagaland

 

Asstt. Agricultural Marketing Adviser,

Directorate of Marketing & Inspection

Regional Office, Rukminigaon,

Navaratna Path, House No. 09,

1st Floor, P.O. Khanapara

Guwahati-781 022 (Assam)

Ph.0361-2229272, 2229273

 

Orissa

 

Marketing Officer

Directorate of Marketing & Inspection

OSCARD Bank Building,

4th Floor, A/34, J N Marg,

BHUBANESHWAR-751001

Ph.0674-2395299

 

Pondicherry

 

Dy.Agricultural Marketing Adviser,

Directorate of Marketing & Inspection

Shastri Bhawan.4 th Floor,

6th Block,26 Handows Roas,

Chennai-600006

Ph.044-28271738,28278065

 

Punjab

Asstt. Agricultural Marketing Adviser,

Directorate of Marketing & Inspection

6th floor Kendriya Sadan,Sector 9’A’ Chandigarh-160047

Ph.0172-2743201

 

 

Rajasthan

 

Asstt..Agricultural Marketing Adviser,

Directorate of Marketing & Inspection

Regional Office, Kendriya Sadan Parisar,

‘A’ Block, 4th Floor, Sector 10,

Vidhyadhar Nagar,

Jaipur- 302023

Ph.0141-2236654

 

 

 

Sikkim

Asstt.Agricultural Marketing Adviser,

Directorate of Marketing & Inspection,

General pool Offices Building,

4th Floor, A Wing, DF Block,

Sector-1,Salt Lake,

Kolkata-700064

Ph.033-23340845,23347553

 

Tamil Nadu

 

Dy.Agricultural Marketing Adviser,

Directorate of Marketing & Inspection

Shastri Bhawan.4 th Floor,

6th Block,26 Haddows Roas,

Chennai-600006

Ph.044-28271738,28278065

 

Tripura

Asstt. Agricultural Marketing Adviser,

Directorate of Marketing & Inspection

Regional Office, Rukminigaon,

Navaratna Path, House No. 09,

1st Floor, P.O. Khanapara

Guwahati-781 022 (Assam)

Ph.0361-2229272, 2229273

 

Uttar Pradesh

Asstt.Agricultural Marketing Adviser,

Directorate of Marketing & Inspection

Regional Office, 5th Floor,  Hall No.2,

Kendriya Bhawan, Aliganj,

Lucknow-226024

Ph. 0522-2326658

 

Uttranchal

Asstt. Agricultural Marketing Adviser,

Directorate of Marketing & Inspection,

Computer Room,

APMC, Nirnjanpur,

Dehradun,

Ph. 0135 – 2521493

 

West Bengal

 

Asstt. Agricultural Marketing Adviser,

Directorate of Marketing & Inspection,

General pool Offices Building,

4th Floor, A Wing, DF Block,

Sector-1,Salt Lake,

Kolkata-700064

Ph.033-23340845,23347553


 

For further information, please contact

 

 

 

Shri S.C.Shah,                                                               Shri J.G.Menon,

Senior Marketing Development Officer,                          Chief General Manager,

Directorate of Marketing & Inspection,                           National Bank for Agriculture &

(Department of Agriculture & Cooperation),                    Rural Development, Plot No. 24,

New CGO Building, NH-IV, Faridabad-121 001              G Block, Bandra Kurla Complex,

Tele : 0129-2412518                                                       Bandra East, Mumbai – 400 051

(Telefax) 0129-2416568, 0129-2412835                          Tele : 022-26539333

E-Mail: vn.swamy@nic.in                                              Fax:   022-26530090

                                                                                    E-mail : icd@nabard.org 

 

Shri Badrul Hasan,                                                        Shri S.R.Singh,

Executive Director             ,                                          Asstt Director,

National Cooperative Development Corporation,             National Institute of Agricultural

4, Siri Institutional Area, Hauz Khas,                              Marketing, Kota Road, Bambala,

New Delhi – 110016                                                     Near Sanganer, Jaipur- 303 906

Tel: 011-26567475                                                         Tele: 0141-2795132, 2775119,

Fax: 011-26961170                                                        Fax : 0141-2770589, 2770051

Email: hasan@ncdc.in                                                    E-mail: sattramsingh@rediffmail.com